Explain Precedence Diagramming Method with Examples

by Mak
March 13, 2021
in Project Management
0
Explain Precedence Diagramming Method with Examples

Explain Precedence Diagramming Method with Examples

2
SHARES
7
VIEWS
Share on FacebookShare on Twitter

Precedence Diagram

A Diagram in which Activities are represented as Nodes, linked by Arrows which represent sequence in which activities stop or start is called precedence diagram.

PDM includes four Dependencies (Precedencies) or Logical Relationships between Activities

  • Finish-to-Start
  • Start-to-Start
  • Finish-to-Finish
  • Start-to-Finish

Predecessor Activity is the one that logically (chronologically) comes before the Successor Activity

A Dependent Activity is the one that is dependent on another Activity for Start or Stop. Usually, but not always, the Successor Activity

Explain Precedence Diagramming Method with Examples
Explain Precedence Diagramming Method with Examples
Finish-to-Start (FS)
  1. Dig Foundation
  2. Pour Concrete

Pouring of Concrete (successor) can only Start after Foundations (predecessor)have been dug

Start-to-Start (SS)
  1. Pour Asphalt
  2. Level & Compress the Road
  • Levelling & Compressing of the Road (successor) can only Start after the Pouring of Asphalt (predecessor)has Started
Finish-to-Finish (FF)
  1. Write a Document
  2. Edit the Document

Editing the Document (successor)can only Finish if Writing the Document (predecessor)has finished

Start-to-Finish (SF)
  1. Old Account Payable
  2. New Account Payable

Old Account Payable (predecessor)can be Shut Down only once the New Account Payable (successor)Starts

Mandatory & Discretionary Dependencies
Mandatory Dependencies

Physically or Legally binding Dependencies.  Like, Superstructure can only be erected AFTER Foundations have been built

  • Also known as Hard Logic
Discretionary Dependencies

Dependencies desired for any particular reason, like Good Practice.  Plumbing and Electrical work can be done in parallel but Good Practice is to Start Electrical work after Plumbing work has completed, to reduce Risk

  • Also known as Preferred or Soft Logic
Internal Dependencies

Within the control of Project Team.  Like, a machine must be Assembled before it can be Tested.

External Dependencies

Dependencies not within the control of the Project Team, one of the Activities being outside the Project Domain.  Like, a customer wants some special Spanish tiles in bathrooms for which an order has been placed on the OEM.  The tiles must be Shipped before they can be Installed.

Lead vs Lag activity
Lead

Amount of Time a Successor Activity can be Advanced with respect to the Predecessor Activity, for any reason.  E.g. Start Editing the Document 2 weeks before Scheduled Completion Date of its Draft

Lag

Amount of Time a Successor Activity is Delayed with respect to the Predecessor Activity, for any reason.  E.g. start 1stFloor Masonry Work 10 days AFTER Pouring Ground Floor Slab, to allow for adequate curing of Slab

Explain Precedence Diagramming Method with Examples

Author

  • Mak

    Learner

    View all posts

Tags: Dependent activitydiscretionary dependenciesExternal depedenciesfinish-to-finishfinish-to-startinternal dependencieslead vs laglead vs lag activitymandatory dependenciesPrecedence diagramPrecedence diagramming methodPredecessor activitystart-to-finishstart-to-start
Previous Post

Tools for Project Resources Estimation with Examples

Next Post

Earned Value Analysis (EVA) Concepts and Formulas

Next Post
Earned Value Analysis (EVA) Concepts and Formulas

Earned Value Analysis (EVA) Concepts and Formulas

Leave a Reply Cancel reply

Your email address will not be published. Required fields are marked *

Facebook Twitter LinkedIn Pinterest Instagram

Recents

  • Marketing on Instagram – A Strategy to Leverage Instagram Influencers
  • Software Project Specification Requirements – Topi Application example

Pages

  • About Us
  • Marketing Research
  • Privacy Policy
No Result
View All Result
  • About Us
  • Marketing Research
  • Privacy Policy

© 2020 Marketing Skull - A School of MarketingMarketing Skull.

Welcome Back!

Login to your account below

Forgotten Password?

Retrieve your password

Please enter your username or email address to reset your password.

Log In
Go to mobile version